Project Status
New Logan ES @ Clague News – December 2025
Current Work, Weather Permitting:
- Utility work continues, including water main work which is about 50% done.
- Structural steel installation and masonry is ongoing.
- Work on the Geothermal Heating, Cooling & Ventilation system continues and is expected to take about 2-3 more months.
- Drilling crews typically operate from 7am to 7pm Monday through Saturday, within the City of Ann Arbor Noise Ordinance.
- Cross Laminate Timber (CLT) installation will be starting in January.

Clague vehicle traffic patterns are identified in blue below. Reminder: The entry is now accessible from Bluett. Entry is no longer available from Nixon Road.

Updates
To support the construction of New Logan Elementary on the Clague Middle School campus, tree felling & site improvements start March 18th. While this can be a noticeable change as vegetation is removed and trees are coming down, AAPS values embodied carbon and is committed to environmental sustainability. To read more about AAPS’ efforts regarding tree salvaging, please follow this link.
Board of Education Meeting – Capital Program Fall Update
Board of Education Meeting – Capital Program Annual Report
Community Engagement with Parents, Student, Staff
Project Kick-off
Projects
-
New Logan Elementary
Architect of Record: Stantec
Construction Manager: The Christman Company
-
Community Engagement - New Logan Elementary
Ann Arbor Public Schools plans to construct a New Logan Elementary, with related site improvements, slated for groundbreaking as early as Spring 2025. Please join us for a Bond Project Update, we will have Phase 2 Bond Plan background information and a conceptual site plan to share.Come to the school’s main entry and you will be directed to the space in the building where the update is being held. We look forward to seeing you!
Tuesday, September 24, 2024 from 5:30pm to 7pm
Logan Elementary: 2685 Traver Blvd, Ann Arbor, MI 48105
-
Paving Project
Repair and rebuild some of the parking areas.
-
HVAC Building Management System Upgrades
Updated the school’s Building Management System (BMS) to the latest version including a new graphical interface and mobile, cloud-based access. The upgrades allow for better systems control, improved occupant comfort and energy efficiency.
-
Water Bottle Filling Stations
Installation of filtered water bottle filling stations throughout the school.
-
Security Updates
Update to security system on property.
-
Playground Shaded Trees
Planted 12 native hardwood trees for shading of playgrounds and other outdoor environments.
-
New Playground Equipment
New playground equipment added to existing space. New items include a run zip track, tri-runner, space whirl and climbing net.
-
Parking Lot Repairs
Repair of pavement and parking lot on school grounds.
-
New Musical Instruments
Purchase of new musical instruments and pianos for music classrooms and auditoriums.
-
New Classroom Furniture
New, flexible, classroom furniture was added to create a more accessible, engaging and student-centered environment.
-
Tree Felling & Site Improvements at Clague Middle School Campus
To support the construction of New Logan Elementary, tree felling & site improvements start March 18th. While this can be a noticeable change as vegetation is removed and trees are coming down, AAPS values embodied carbon and is committed to environmental sustainability. To read more about AAPS’ efforts regarding tree salvaging, please follow this link.
Photos & Videos
Photos
Videos
Timeline
Logan Elementary
- Built In 1977
- Grades Young 5-5th
- School Website
Logan Elementary, originally constructed in 1977, is a one-story masonry structure with exterior brick veneer. The school facility is situated on 9.75 acres in the northeast sector of Ann Arbor. The original structure has experienced 1 addition over the years, and currently supports Young 5 – Grade 5 education.
























